UAE Construction Law: Can Contractors Seek Legal Relief When Project Costs Escalate?

UAE Construction Law: Can Contractors Seek Legal Relief When Project Costs Escalate?

New Civil Transactions Law allows courts to restore contractual balance when exceptional events cause severe financial disruption.

AuthorStaff WriterNov 17, 2026, 8:49 AM

Construction projects are often exposed to geopolitical tensions, international conflicts and interruptions to global supply chains. Armed conflicts, trade restrictions, shipping delays and sudden increases in the prices of essential building materials can place considerable pressure on project budgets and delivery schedules. For contractors operating in the UAE, this raises an important legal issue: under what circumstances can an unexpected rise in the cost of executing a construction contract justify a revision of the agreed contractual obligations?

 

The UAE Civil Transactions Law, enacted through Federal Decree-Law No. 25 of 2025 and effective from 1 June 2026, establishes a framework for dealing with exceptional events that substantially disturb the balance between contracting parties. Article 224 deals with unforeseen exceptional circumstances, while Article 829 provides a specific mechanism for restoring financial equilibrium in construction contracts. Both provisions are relevant when external developments impose an unusually heavy financial burden on the completion of a project.

 

When Exceptional Circumstances Justify Relief

 

Article 224 of the Civil Transactions Law deals with exceptional and general circumstances that were not reasonably foreseeable when an agreement was entered into. If such circumstances make the performance of an obligation excessively burdensome for the debtor and expose that party to serious loss, the court may consider the interests of both parties and reduce the obligation to a reasonable level or order the termination of the contract. Any contractual provision intended to exclude the application of this article is void.

 

The provision acknowledges that obligations which were commercially reasonable when an agreement was signed may become disproportionately difficult to fulfil because of developments outside the parties' reasonable expectations. In the construction sector, possible examples include armed conflicts, major trade restrictions, interruptions to important shipping routes, export bans and extraordinary increases in the prices of essential construction materials.

 

However, the existence of an external disruption or an increase in expenditure does not, by itself, establish grounds for legal relief. The event must be exceptional, general in character and unforeseeable when the contract was concluded. Its consequences must also be sufficiently severe to threaten substantial financial loss. Routine market movements, anticipated inflation, inaccurate project estimates and ordinary commercial misjudgements would not normally meet this standard.

 

Hardship And Force Majeure Are Not The Same

 

It is important to distinguish between hardship and force majeure, as the two legal concepts deal with different consequences arising from events beyond the reasonable control of contracting parties.

 

Force majeure is governed by Article 236 of the Civil Transactions Law. In bilateral contracts, if an event of force majeure makes performance impossible, the corresponding obligations are extinguished and the contract is automatically rescinded. Where the impossibility affects only part of the obligation, that part may be extinguished, or either party may seek rescission. If the impossibility is temporary in a continuing contract, an appropriate modification or rescission may be considered, depending on the circumstances.

 

Hardship applies where contractual performance remains possible but has become excessively onerous. A contractor, for instance, may still be able to procure steel, cement or specialised equipment through alternative suppliers or shipping routes, but at considerably higher prices and with substantial logistical complications. Although these difficulties may not make performance impossible, they could amount to hardship if the additional burden threatens serious financial loss and meets the statutory conditions.

 

Contractors should consequently avoid treating every increase in procurement costs or disruption to supplies as a force majeure event. The appropriate legal remedy will depend on how the particular circumstances affect the ability to fulfil the contractual obligation.

 

How Article 829 Changes The Position For Construction Contracts

 

Alongside the general hardship provision, Article 829 establishes a specific framework for Muqawala agreements, which include construction contracts. Under Article 829(1), where a Muqawala contract is based on an agreed design for a fixed lump-sum payment, the contractor is generally not entitled to demand an increase in the contract price simply because material, labour or other costs have risen. Article 829(2) also regulates changes and additions to the agreed design, subject to the specified exceptions involving the employer's fault or authorisation and agreement on additional remuneration.

 

A significant qualification appears in Article 829(3). Where general exceptional circumstances, which could not reasonably have been anticipated when the contract was signed, disturb the financial equilibrium between the employer and contractor and undermine the economic basis on which the agreed price was calculated, the court may order appropriate measures to restore the balance. These may include extending the project completion period, increasing or reducing the agreed remuneration, or rescinding the contract.

 

The provision has particular relevance to major infrastructure developments and long-duration construction projects involving substantial procurement commitments and extended implementation schedules. It recognises that, in genuinely exceptional situations, insisting on the original price and completion requirements may no longer reflect the commercial assumptions underlying the agreement.

 

Nevertheless, Article 829 should not be interpreted as giving contractors an automatic right to additional compensation whenever project expenditure rises. It is necessary to establish that exceptional circumstances have materially disturbed the contractual equilibrium, rather than simply affected the contractor's expected profit.

 

Why Notice And Documentary Evidence Matter

 

A party seeking relief must establish both the exceptional nature of the circumstances and their actual consequences for contractual performance. While Articles 224 and 829 do not prescribe a particular notice period or an exhaustive list of supporting documents, meeting contractual notification requirements and maintaining reliable contemporaneous records can be critical to the success of a claim.

 

Contractors should preserve supplier quotations, purchase orders, revised invoices, shipping notices, insurance costs and comparisons of material prices before and after the relevant event. Where project delays are involved, construction programmes, delivery schedules, supplier correspondence and critical path analyses may help demonstrate the extent to which the disruption affected the completion date.

 

Particular attention should be paid to contractual notice provisions. Construction agreements commonly specify time limits and procedures for notifying employers about events that could affect project costs or delivery schedules. Failure to follow these requirements can complicate a claim, even where the underlying circumstances are genuinely exceptional.

 

Evidence of reasonable mitigation is equally important. Contractors should be able to demonstrate that they considered alternative suppliers, different procurement channels and substitute materials, wherever such options were commercially and practically available. A party seeking relief may find it difficult to justify the full financial impact of a disruption without showing that reasonable steps were taken to limit its consequences.

 

Preparing Contracts For Future Cost Disruptions

 

The new statutory framework reinforces the need for more precise risk-allocation provisions in construction agreements. Long-term infrastructure and building contracts should clearly distinguish between force majeure, exceptional hardship and ordinary price escalation. They should also address mechanisms for adjusting material costs, defined thresholds for significant increases, notification periods, documentary requirements and the circumstances in which extensions of time or additional payments may be considered.

 

Contracting parties should also examine how Article 829(3) applies to their agreements, particularly because it does not expressly contain the same prohibition against excluding the provision that appears in Article 224. Existing agreements also require careful consideration of the governing law and the transitional arrangements under Article 4, which establishes the general principle against retrospective application of the new legislation.

 

The UAE legal framework does not give contractors an unrestricted right to pass every unexpected increase in construction expenditure on to employers. It does, however, recognise that exceptional developments may warrant judicial intervention where they substantially disturb the contractual balance and undermine the financial assumptions on which an agreement was based. Establishing the difference between ordinary commercial difficulty and legally recognised hardship will remain central to determining whether contractual obligations can be adjusted.

 