UAE Law Extends Time To Claim Compensation Over Hidden Construction Project Defects

UAE Law Extends Time To Claim Compensation Over Hidden Construction Project Defects

Revised Civil Transactions Law extends the statutory claim period to one year, strengthening protection against latent defects.

AuthorStaff WriterNov 10, 2026, 9:50 AM

The formal handover of a construction project is often viewed as the point at which the contractor has substantially fulfilled its obligations and the employer assumes possession of the completed works. Yet, the completion of a project does not necessarily bring all questions of liability to a close. Defects concealed within the structure or its installations may emerge only after the building has been occupied or its systems have been put into regular operation. Such problems can give rise to disputes long after the initial inspection and handover have taken place.

 

The UAE's revised Civil Transactions Law, introduced through Federal Decree by Law No. 25 of 2025, has brought an important change to the statutory framework governing latent defects. The legislation extends the period for bringing qualifying claims from six months to one year from delivery, unless a longer warranty period has been agreed between the parties. Coming into effect on June 1, 2026, the amendment provides an extended period for seeking remedies in circumstances covered by the law and reinforces the importance of post-delivery responsibilities.

 

Understanding the Legislative Change

 

Under the previous Civil Transactions Law, Federal Law No. 5 of 1985, Article 555 prescribed a six-month period from delivery for claims relating to latent defects. Once that period expired, such claims were generally inadmissible unless the seller had agreed to provide a longer warranty. An exception applied where the seller had fraudulently concealed the defect, preventing reliance on the statutory time restriction.

 

The new legislation revises this position through Article 510, which extends the relevant period to one year, calculated from the day following delivery of the subject matter of the sale. Where the seller has expressly undertaken to provide a longer warranty, the agreed duration may continue to govern. The protection against fraudulent concealment of defects has also been retained.

 

The revised law additionally provides greater clarity on the characteristics of a latent defect. Article 494 generally treats a defect as latent where it existed before delivery but could not have been discovered through an ordinary examination, or where identifying it required specialist expertise, testing or technical investigation. A defect that becomes apparent only after delivery may also qualify if evidence establishes that its underlying cause existed at the time of delivery.

 

This distinction is significant because the appearance of a problem after handover does not automatically make it a latent defect under the statutory framework. The relevant consideration is whether the underlying defect was already present at the time of delivery and whether it could reasonably have been identified through an ordinary inspection.

 

The additional time is particularly relevant in cases where the nature of the defect makes early detection difficult. Some shortcomings become apparent only after the goods or completed works have been exposed to their intended operating conditions, regular use or environmental factors over an extended period.

 

In construction matters, however, Article 510 should not be considered in isolation. Its application needs to be assessed alongside the provisions governing contracts for work under Articles 812 to 839 of the new Civil Transactions Law and the warranty arrangements contained in the relevant construction agreement. The statutory extension concerns qualifying latent-defect warranty claims, but its application to a particular construction contract will depend on the nature of the legal relationship and the obligations assumed by the parties.

 

It is equally important to distinguish this provision from the separate regime of decennial liability under Articles 821 to 824. That regime deals with structural collapse and defects threatening the stability or safety of buildings and fixed structures, and operates independently of the ordinary latent-defect warranty framework.

 

What the Change Means for Construction Projects

 

For employers and project owners, the extended statutory period may provide additional time to discover qualifying defects and pursue appropriate remedies, subject to the applicability of Article 510 and any longer warranty agreed by the parties.

 

Construction-related defects are not always immediately apparent during a handover inspection. Problems involving waterproofing, concealed electrical wiring, plumbing installations, mechanical equipment and building materials may remain undetected until the property has been occupied or the relevant systems have operated for some time. Exposure to changing weather conditions, prolonged use and the demands of normal building operations can reveal shortcomings that were not visible during the initial inspection.

 

For contractors, the amendment reinforces the need to manage responsibilities beyond practical completion. A handover certificate may establish that possession has passed to the employer and that the project has reached the agreed stage of completion. However, it does not necessarily extinguish obligations arising under applicable statutory warranties or contractual provisions relating to defects.

 

The circumstances surrounding the alleged defect will remain central to determining liability. A problem that could reasonably have been identified through an ordinary inspection may be treated differently from one that remained concealed despite appropriate examination. The timing of its occurrence, the point at which it could have been discovered and the contractual responsibilities of the parties may all become relevant when a claim is examined.

 

Consequently, neither the completion certificate nor the expiry of an ordinary inspection or snagging process should automatically be treated as conclusive evidence that all potential defect-related responsibilities have ended.

 

Why Inspection and Documentation Matter

 

The longer period available for certain claims makes proper project documentation and effective inspection procedures particularly important. Employers should ensure that completed works undergo appropriate technical examinations before acceptance. Installed systems should be tested, and any shortcomings identified during the process should be included in detailed snagging records.

 

Defects discovered during inspection should be formally communicated to the contractor. Photographs, technical reports, testing results and inspection records can help establish the nature and extent of the problem and provide a reliable record of the condition of the works at the time of handover.

 

If a defect becomes apparent after possession has been transferred, the employer should notify the contractor promptly and follow the notification procedures prescribed by the contract and applicable law. Delaying communication until the end of the warranty period may make it more difficult to establish when the problem first arose, how it developed and whether its cause existed before delivery.

 

A formal notification should describe the defect clearly, identify the affected installations or areas and explain the corrective measures being requested. Relevant correspondence, photographs, inspection findings and technical assessments should be retained, particularly where there is a possibility that the disagreement could develop into a formal dispute.

 

Contractors have comparable reasons to maintain comprehensive records after project completion. Approved drawings, material specifications, testing certificates, site instructions, variation orders, maintenance information and handover documents may all become relevant when responsibility for an alleged defect is investigated.

 

Such records can help establish whether the problem arose from defective workmanship, unsuitable materials, subsequent modifications, inadequate maintenance or circumstances beyond the contractor's responsibility. Without adequate documentation, distinguishing between an original construction defect and damage arising from later use or intervention can become considerably more difficult.

 

Post-handover complaints should therefore be handled through a structured process. Contractors should arrange appropriate technical investigations, record their findings and communicate their position in writing. Where liability is disputed, an independent technical assessment may also assist in establishing the cause of the problem and narrowing the issues between the parties before formal proceedings become necessary.

 

Reviewing Construction Contracts and Warranty Provisions

 

The legislative amendment also provides a reason for employers, contractors and their legal advisers to revisit existing approaches to defects liability and contractual warranties. Construction agreements should be examined to ensure that their provisions remain consistent with the revised statutory framework.

 

Particular attention should be given to the distinction between a contractual defects liability period and the statutory period for bringing a qualifying claim. These are not necessarily identical concepts and should not be treated as interchangeable. The contractual period may regulate the contractor's obligation to rectify defects identified during a specified period, while the statutory provisions address the legal position concerning qualifying latent defects.

 

Well-drafted construction agreements should clearly establish the duration and scope of warranties, the procedure for reporting defects, the contractor's obligations to investigate and undertake remedial work, and the treatment of concealed defects and recurring failures.

 

The parties should also consider how warranties operate where remedial work is undertaken. If rectification triggers a fresh or extended warranty, the contract should specify when that period begins, which components or works it covers and whether the extension applies to the entire installation or only the repaired portion.

 

Clarity in these provisions can help prevent disagreements over the extent of post-completion obligations and the remedies available when defects emerge after handover.

 

The transitional arrangements under the new legislation are another important consideration. Article 6 provides for the application of the revised rules on limitation periods from June 1, 2026, to periods that have not yet expired. Employers and contractors should therefore review ongoing projects, existing warranties and outstanding defect claims to determine whether the new provisions affect their respective positions.

 

The fact that a construction agreement was signed before the new law came into force does not, by itself, establish that the revised provisions are irrelevant. The status of the relevant claim and the applicable transitional rules will need to be examined in each case.

 

Conclusion

 

The extension of the statutory period for qualifying latent-defect warranty claims from six months to one year represents a significant development in the UAE's civil law framework. By allowing additional time to identify concealed defects and pursue available remedies, the revised legislation strengthens the protection available to parties in circumstances covered by the law.

 

For employers, the change highlights the importance of comprehensive inspections, timely notification and the preservation of technical records. Contractors, meanwhile, need to ensure that their post-handover procedures, documentation practices and contractual warranty arrangements adequately address the revised legal position.

 

Ultimately, the handover of a construction project should not be regarded as the automatic end of every potential responsibility for defects. The period following completion can be just as important as the construction phase itself. Clear contractual provisions, reliable documentation and an effective approach to identifying and addressing defects remain essential to protecting the interests of both employers and contractors and reducing the risk of avoidable construction disputes.

 

For enquiries or further information, contact ask@tlr.ae or call +971 52 644 3004. Follow The Law Reporters on WhatsApp Channels.